- PM Modi visit USAOnly the mirror in my washroom and phone gallery see the crazy me : Sara KhanKarnataka rain fury: Photos of flooded streets, uprooted treesCannes 2022: Deepika Padukone stuns at the French Riviera in Sabyasachi outfitRanbir Kapoor And Alia Bhatt's Wedding Pics - Sealed With A KissOscars 2022: Every Academy Award WinnerShane Warne (1969-2022): Australian cricket legend's life in picturesPhotos: What Russia's invasion of Ukraine looks like on the groundLata Mangeshkar (1929-2022): A pictorial tribute to the 'Nightingale of India'PM Modi unveils 216-feet tall Statue of Equality in Hyderabad (PHOTOS)
India Open Competition in Shotgun, organised by the National Rifle Association of India (N
- Hockey India names Amir Ali-led 20-man team for Junior Asia Cup
- Harmanpreet Singh named FIH Player of the Year, PR Sreejesh gets best goalkeeper award
- World Boxing medallist Gaurav Bidhuri to flag off 'Delhi Against Drugs' movement on Nov 17
- U23 World Wrestling Championship: Chirag Chikkara wins gold as India end campaign with nine medals
- FIFA president Infantino confirms at least 9 African teams for the 2026 World Cup
Delhi Metro's 'Heritage Line' at final checkpoint Last Updated : 18 Mar 2017 07:20:47 AM IST File photo
The long-awaited "Heritage Line" of Delhi Metro inched closer to being pressed into service, as the DMRC submitted papers to the safety department on Friday for approval -- the last step before the metro becomes available to commuters.
The Delhi Metro Rail Corporation (DMRC) submitted papers for the line connecting ITO and Kashmere Gate (5.17 km) to the Commissioner for Metro Railway Safety (CMRS) and also to the Independent Safety Assessor (ISA) for certification, after which the line will be opened to the general public.
"The documents will be scrutinised by CMRS office and thereafter a CMRS inspection will be planned. The line will be opened for public after safety certification of signalling system by the ISA," a statement issued by the transporter read.
A part of the Violet Line (ITO-Escorts Mujesar), the stretch was originally scheduled to be completed by December 2015 but missed several deadlines before its first trial-runs could be conducted in August last year.
"This was a challenging line from the very beginning. We had to execise extra caution during the construction because of the stretch being dotted with structures of historical value all along it. It also took us longer than usual time in getting clearance and securing landspace this time," a DMRC official told media.Given the recurring delays, he could not bring himself to commit to any time-frame and say when the metro would become commuter-ready.
"I cannot commit any time. Earlier, there have been instances when we were given permission in a day. Not sure about now, it may take month or even more," he said.IANS For Latest Updates Please-
Join us on
Follow us on
172.31.16.186